A federal judge temporarily blocked construction of the controversial Keystone XL pipeline, ruling late Thursday that the Trump administration had failed to justify its decision granting a permit for the 1,200-mile long project designed to connect Canada’s tar sands crude oil with refineries on the Texas Gulf Coast.
It was a major defeat for President Trump, who attacked the Obama administration for failing to move ahead in the face of protests based largely on environmental concerns. Trump signed an executive order two days into his presidency setting in motion a course reversal on the Keystone XL pipeline and the Dakota Access pipeline.
The decision, issued by Judge Brian Morris of the U.S. District Court for the District of Montana, does not permanently block a permit but requires the administration to conduct a more complete review of potential adverse impacts related to climate change, cultural resources and endangered species. It basically ordered a do-over.
Morris hit the administration with a familiar charge, that it disregarded facts, facts established by experts during the Obama administration about “climate-related impacts” from Keystone XL. The Trump administration claimed, with no supporting information, that those impacts “would prove inconsequential.” The State Department “simply discarded prior factual findings related to climate change to support its course reversal.”
It also used “outdated information” about the impact of potential oil spills on endangered species, he said, rather than “’the best scientific and commercial data available.’”
“Today’s ruling makes it clear once and for all that it’s time for TransCanada to give up on their Keystone XL pipe dream,” said Sierra Club Senior Attorney Doug Hayes in a statement. The lawsuit prompting Thursday’s order was brought by a collection of opponents, including the indigenous Environmental Network and the Northern Plains Resource Council, a conservation coalition based in Montana.
“The Trump administration tried to force this dirty pipeline project on the American people, but they can’t ignore the threats it would pose to our clean water, our climate, and our communities,” Hayes said.
Hayes told The Washington Post that the company had already been moving equipment into place in Montana and South Dakota with the intent of beginning construction in early 2019.
“It’s clear that this decision tonight will delay the pipeline significantly,” said Hayes, who noted that a proper environmental impact statement of this scope usually takes about a year to complete. “TransCanada does not have an approved pipeline at this point.”
[Read the decision]
Morris, a former clerk to the late Chief Justice William Rehnquist, was appointed to the bench by President Obama. His decision was one of scores of court rebukes to the Trump administration for decisions on the environment, immigration and transgender service in the military, among other issues, made hastily and, in the opinions of dozens of judges, without the “reasoned consideration” required by various federal laws, particularly the Administrative Procedure Act. Also on Thursday, a federal appeals court ruled that Trump cannot immediately end the program, DACA, that shields from deportation young undocumented immigrants who were brought to the country as children.